Microsoft exits Nscale's UK AI data centre project amid power capacity delays

2 reports2 sources10/19/2026 updated

Current overview (not historical)

AI overview

Microsoft has terminated its involvement in Nscale's planned UK AI data centre in Loughton, Essex, citing unresolved power capacity issues. UK Power Networks indicated capacity may not be available until the early-to-mid 2030s, prompting Microsoft to abandon the project. Nscale continues planning a 2 billion pound project for 2026 and maintains that its overseas cooperation with Microsoft remains strong, while Microsoft declined to comment.

Written with AI from the reporting · updated 10/19/2026

Expand the detailed fact route and sources

Story route

A station-by-station route from the first public evidence onward; every station carries its own evidence and uncertainty.

  1. 1Unclassified fact stationOct 19, 07:40single sourcereport-time onlyrevised

    Microsoft terminates involvement in UK's largest AI data cen

    Read original source ↗ BBC BusinessReplay this moment in the explorer
    Evidence & revisions · 1 source records
    Subject:
    microsoft
    Action:
    terminated involvement
    Object:
    Nscale's AI data centre project in Loughton, Essex
    Occurred (fact side):
    not recorded
    BBC Business ↗Report pageRevision 2 · currently revised
    Published (valid side):
    Oct 19, 00:46
    First seen (known side):
    Oct 19, 07:40
    Fact stationSingle source · one-sided claimRevisedReport-time only

    Copy may have been revised later; time replay is bounded. Layer labels group reading only, not causation between layers.

  2. 2Unclassified fact stationOct 19, 00:00recorded Oct 19, 19:52single sourcerevised

    Nscale loses Microsoft AI data center deal due to power dela

    Read original source ↗ CoinDeskReplay this moment in the explorer
    Evidence & revisions · 1 source records
    Subject:
    Nscale
    Action:
    loses Microsoft AI data center deal
    Object:
    Microsoft Azure cloud data center project in Loughton, Essex
    Occurred (fact side):
    Oct 19, 00:00
    CoinDesk ↗Report pageRevision 2 · currently revised
    Published (valid side):
    Oct 19, 17:15
    First seen (known side):
    Oct 19, 19:52
    Fact stationSingle source · one-sided claimRevised

    Copy may have been revised later; time replay is bounded. Layer labels group reading only, not causation between layers.

Uncertainty marks flag where to check the sources; they are not proven causation.

Report timeline

Explore every side through dated source reports.

Oct 19
  1. CoinDeskRelated fact: single sourceSource report revised
    Nscale loses Microsoft AI data center deal over U.K. power grid delays stretching into 2030s

    Report first recorded Oct 19, 19:52

    Microsoft abandoned a planned Nscale AI data center in the U.K. after the local grid operator UK Power Networks said sufficient power may not be available until the early-to-mid 2030s. The facility was expected to supply 50 megawatts of computing capacity to Microsoft Azure using 23,040 Nvidia chips by early 2027.

    Read original source ↗
  2. BBC BusinessRelated fact: single sourceFact occurrence time unverifiedSource report revised
    Microsoft exits UK's largest planned AI data centre project

    Report first recorded Oct 19, 07:40

    Nscale announced plans to build the UK's largest AI data centre in Loughton, Essex, with a £2 billion investment. Microsoft had pledged to fund a supercomputer at the site but has since terminated its involvement. Nscale says it is exploring alternative power sources and maintains that its relationship with Microsoft remains strong for other overseas projects.

    Read original source ↗